Client challenge:
Significant project changes with short notice.

40,000 sq. ft. Recreation Center
2 weeks before the construction documents were due, the design in a number of areas underwent changes.
About 9 sheets of interior elevations and finish documents had to be modified.
Client's in-house team was unable to implement the changes.

Solution:
We were able to step in at this crucial time for the client and quickly take over this task for them. We were able to turn this part of the project around in less than 2 weeks. We thus helped the client keep their deadline with a completed and accurate set of documents.